Tauranga City

All Maintenance Updates by Fulton Hogan in the Tauranga City Area

What’s happening in Tauranga?

Tauranga City Council has contracted Fulton Hogan Ltd to carry out repairs and maintenance in Tauranga City.

This work is part of the Council’s annual programme, improving road safety and investing in our roading assets, including footpaths.

Our work is very weather dependant so dates may change due to the weather or other unforeseen circumstances.

Our roadworks include heavy machinery which unfortunately can create noise, vibration and types of environmental factors (including cement dust for example).

Strathmore Street Minor Berm Repairs

Status: ACTIVE

Date of Works: TUESDAY 22ND APRIL 2025

Type of Works: Minor Berm Repairs

This work includes removing the concrete, bricks and install a grass berm.

Additional Information:

The site will be left sectioned off for approximately 6 to 8 weeks to allow for the grass seed to grow. All work will be carried out under a shoulder closure to keep disruption to a minimum.

Beaumaris Boulevard Asphalt Surfacing

Status: ACTIVE

Date of Works: WEDNESDAY 23RD & THURSDAY 24TH APRIL 2025

Type of Works: ASPHALTING

These dates are subject to change, and we advise that you check the website below for updates.

As part of the staging for these works, you will experience a temporary road surface with level changes. Please drive carefully through the site.

Additional Information:

All work will be carried out under a shoulder closure to keep disruption to a minimum.

The team plans to finish over the Easter break. However, the program is weather-dependent and therefore if progress is affected the works will be completed the following week during night shifts.

Ranginui Road Winter Maintenance

Status: COMPLETED

Date of Works: THURSDAY 10TH APRIL 2025

Type of Works: WINTER MAINTENANCE

This work includes cleaning out of culverts, replacing post that mark the edge of the road, and a culvert repair.

Additional Information:

All work will be carried out under a shoulder closure to keep disruption to a minimum.

Matapihi Winter Maintenance

Status: COMPLETED

Date of Works: MONDAY 31ST MARCH TO FRIDAY 4TH APRIL 2025

Type of Works: WINTER MAINTENANCE

This work includes cleaning out of culverts, excavating a new swale drain, bollard installation, and a culvert replacement. All work will be carried out under a shoulder closure to keep disruption to a minimum.

Additional Information:

The 4 highlighted areas below indicates the working areas. Please note that this site will be operating under shoulder closures.

Stage one: Matapihi Station Road. This is programmed for Monday 31st March 2025 – Wednesday 2nd April. This work includes escavating a new swale drain and installing bollards.

Stage two: Matapihi Road. This is programmed for Wednesday 2nd April 2025 – Thursday 3rd April 2025 starting with the left photo. This work includes replacing the culvert outside of 494 Matapihi Road, and clearing of culvert inlets and outlets.

Stage three: Puwhariki Road. This is programmed for Friday 4th April 2025. This work includes cleaning culvert inlet and outlets.

Carmichael Road and St Michaels Avenue Asphalt

Status: ACTIVE - RETURN TO COMPLETE

Date of Works: MONDAY, 28TH APRIL 2025

Type of Works: ASPHALTING

Please note that these works must be undertaken at night due to the traffic volumes during the day and being unable to maintain traffic access during these works. These dates are subject to change, and we advise that you check the website below for updates.

As part of the staging for these works, you will experience a temporary road surface with level changes. Please drive carefully through the site.

Additional Information:

Please note that this site will be operating under Stop/ Go. Please allow extra time when travelling through the site.

Briarley Street Cul-de-sac Asphalt Resurfacing

Status: DELAYED

Date of Works: FRIDAY 21ST FEBRUARY 2025

Type of Works: ASPHALTING

Fulton Hogan Ltd will be returning to site to replace a small section of the asphalt surface, as it does not meet our desired quality standards. We apologize for any inconvenience this may cause and assure you that our team will work efficiently to complete the project promptly.

 

Additional Information:

Please note the BLUE highlighted section of road will be under a stop/go while works is undertaken. Residents and businesses will still be able to access their properties, we ask that you allow extra time in case machinery is working directly outside your driveway as it can take some time to make a passage for you to enter/exit.

KOROMIKO STREET ASPHALT SURFACING

Status: COMPLETED

Date of Works: TBC 2025

Type of Works: ASPHALT SURFACING

Fulton Hogan Ltd will be returning to site to replace a small section of the asphalt surface, as it does not meet our desired quality standards. We apologize for any inconvenience this may cause and assure you that our team will work efficiently to complete the project promptly.

Additional Information:

Please note that this site will be operating under a road closure during the works and you should allow additional time when travelling through the site.

Read More